根據青(qing)島地鐵集(ji)團有限公司企業標準(zhun)(zhun)Q/QD-GC-G-SJ-37—2017《土建(jian)工(gong)程開(kai)工(gong)條件(jian)驗收管(guan)理規(gui)定》,規(gui)定了青(qing)島地鐵主(zhu)體及附屬工(gong)程開(kai)工(gong)前驗收準(zhun)(zhun)備(bei)工(gong)作(zuo)及開(kai)工(gong)前驗收標準(zhun)(zhun)。
按照規定要求,2020年4月14日(ri),由(you)青島地鐵(tie)集(ji)團工(gong)程(cheng)(cheng)建設分公司(si)組織(zhi)勘察單(dan)(dan)位、設計單(dan)(dan)位、監(jian)理(li)單(dan)(dan)位、施(shi)工(gong)單(dan)(dan)位、第三(san)方監(jian)測等參建單(dan)(dan)位對中(zhong)鐵(tie)三(san)局施(shi)工(gong)的TBM始(shi)發(fa)井進行(xing)(xing)了(le)(le)開(kai)工(gong)條(tiao)件驗(yan)收工(gong)作。各單(dan)(dan)位首先(xian)對施(shi)工(gong)現場進行(xing)(xing)了(le)(le)外業(ye)檢(jian)(jian)查,然后在中(zhong)鐵(tie)三(san)局項(xiang)目部(bu)會議室對內業(ye)資料(liao)進行(xing)(xing)檢(jian)(jian)查,中(zhong)鐵(tie)三(san)局工(gong)程(cheng)(cheng)部(bu)匯(hui)報(bao)了(le)(le)關于TBM始(shi)發(fa)井的工(gong)程(cheng)(cheng)概(gai)況、目前(qian)工(gong)作進展情況以及開(kai)工(gong)條(tiao)件資料(liao)準備情況,市(shi)政管(guan)理(li)處領導全(quan)程(cheng)(cheng)監(jian)督并對各項(xiang)內業(ye)資料(liao)進行(xing)(xing)了(le)(le)詳細查看(kan),針對現場安全(quan)、質量、文明施(shi)工(gong)提出(chu)相關指導性意見。
經過各(ge)方(fang)單位按照青島地鐵集團(tuan)有(you)限公司企業標準(zhun)Q/QD-GC-G-SJ-37-2017《土建工程開工條件驗收管理規定》及驗收流(liu)程,經過施工單位自(zi)檢自(zi)評,監理單位預審,TBM始發井一期工程調整方(fang)案(an)(輪渡站(zhan)(zhan)~泰(tai)山(shan)路站(zhan)(zhan)段)開工條件驗收工作(zuo)順利通過。
地鐵2號線西延段TBM盾(dun)構掘進(jin)段長約2.88千米,占西延段全(quan)(quan)長的(de)3/4,盾(dun)構機(ji)施工(gong)范圍(wei)自輪渡站(zhan)始發井至泰山路站(zhan)折返線,計劃2021年3月開(kai)始區間掘進(jin)施工(gong)。中鐵三局全(quan)(quan)體員工(gong)將嚴(yan)格按照上級單位相(xiang)關要求,把安全(quan)(quan)生產擺在首(shou)位,保(bao)質保(bao)量完成(cheng)好地鐵2號線一期(qi)工(gong)程建設任務。
- 青島市地鐵規劃設計院有限公司 2021年第二次社會招聘公告 2022-05-24
- 青島市地鐵規劃設計院有限公司 2021年第一次社會招聘公告 2022-02-25
- 戰“疫”復工在行動益群公司進一步完善地鐵大廈疫情防控措施 2021-03-09
- 青島地鐵集團成功舉辦 2號線車輛基地高壓觸電事故應急演練 2017-01-27
- 青島地鐵工程建設安全質量隱患排查系統正式上線試運行 2017-01-27